Bankside Sub-Station Modernisation, London

Commercial management services to this £19 million project delivered under the ICE 7th standard form of contract. Responsible for the contract administration of a number of specialist trade contract packages to this complex project that had to be undertaken through multiple phasing, reflecting both the sensitive environment precipitated by the links with Tate Modern; and the necessity to retain power supplies from the sub-station throughout construction.

17 Jan 2017