Case studies

Case Study

Hilden Grange School, Tonbridge

DGA were commissioned by the client to provide a full planning and programming service. Initially, to prepare a Strategic Programme of Works under RIBA Stage B requirements, and update in respect of external events. The service then included commentary and advice on contractor’s tender programmes, and the agreement of the Contract programme with the successful tenderer. We were then asked to monitor the progress of the works and determine the impact of all relevant events.

20 Jan 2017